A reseller in Warsaw needed a Christmas campaign ready by mid-November. She placed a bulk order on October 15 expecting two weeks based on the supplier website. The factory needed 28 days for plating and QC, customs added 6, and the parcel landed November 26. She missed the campaign and never reordered from that supplier. She came to us the following year and we walked her through a sample-first, bulk-second timeline that hit the date exactly.
Lead time is the number new wholesale buyers get wrong most often. Here is how our own schedule actually runs, and how to plan a campaign date backwards from it.
01The two clocks: sample and bulk
We run two separate production lanes. Samples are small, prioritized, and deliberately quick. Bulk runs in queues and includes plating, QC and packing.
| Order type | What it includes | Our standard lead time | Expedited |
|---|---|---|---|
| Sample (1 to 5 pcs) | Pull from existing stock or quick-set | 3 to 5 days | 2 days (+30%) |
| Sample, custom design | CAD, wax, set, plate | 12 to 18 days | 9 days (+40%) |
| Bulk, open-stock items | Pull, QC, pack, ship | 7 to 10 days | 5 days (+25%) |
| Bulk, made-to-order | Set, plate, QC, pack | 20 to 30 days | 16 days (+30%) |
| Bulk, private label | Carding, boxing, labeling | 30 to 45 days | 25 days (+35%) |
The longest lane is private label, because printing custom cards and boxing adds a week on top of production. If your campaign depends on custom packaging, build that into the plan.
02Shipping on top of production
Production time is factory time. Shipping time is separate and varies by destination:
- DDP to US: 5 to 8 days after dispatch.
- DDP to EU/UK: 5 to 10 days, plus 1 day for customs clearance.
- Express courier (DHL/FedEx): 3 to 5 days worldwide, at roughly double the DDP rate.
Plan backwards from your campaign date: production plus shipping plus 3 days buffer. The Warsaw buyer above should have ordered by October 5, not October 15, to hit November 15.
Plan backwards from your campaign date: production plus shipping plus 3 days buffer. The Warsaw buyer above should have ordered by October 5, not October 15, to hit November 15.
03Why samples come first
A sample order costs more per piece but saves the bulk order. A $40 sample parcel, checked on your own wrist or in your own display light, catches four things before you commit $5,000 to bulk: plating thickness, stone color, clasp function and size feel. We refund the sample cost against the first bulk order, so the sample effectively costs nothing if you proceed. Samples also lock the spec. When bulk runs, the production team compares the bulk lot against your approved sample, not against the website photo. That removes the it looked different in person complaint from the equation.
04What slows bulk orders down
Four things eat lead time, in our experience:
- Custom stone sizes. Anything outside our calibrated 3/4/5/6.5mm rounds goes to a separate cutting queue.
- Mixed plating in one order. Plating barrels are set per finish. Mixing rhodium, gold and rose gold in one batch triples plating time.
- Private-label carding. Artwork approval alone takes 3 to 5 days on average; start it before production starts.
- EU nickel-free rerun. If a first batch fails our in-house nickel test, the rerun adds 7 to 10 days. We test at incoming inspection to avoid this.
For the regulatory side of EU orders, see REACH nickel compliance for EU wholesale. For what is actually happening on the floor during those lead times, walk the factory production flow.
05Frequently Asked Questions
How early should I order for a Christmas campaign?
For EU/UK delivery by December 1, bulk order must ship from our factory by November 5. That means placing the order around October 5 for made-to-order, October 15 for open-stock. Always add a 3-day buffer.
Do you offer rush production?
Yes, at 25 to 40% upcharge depending on lane. Rush cuts plating and QC slightly, so we only recommend it for open-stock reorders, not new designs.
Can I cancel a bulk order after it starts production?
Free cancellation before production starts. After production starts, we charge 30% to cover stone and alloy cost. After plating, no cancellation; the pieces are finished to your spec and cannot be resold as easily.
How do you track my order?
We send a photo update at three milestones: stone setting done, plating done, QC passed. DDP shipments include a tracking number from dispatch. You can also request a live video walkthrough of your lot at QC.
What happens if a shipment is delayed?
We notify you the same day we see a slip, and we split-ship: what is ready goes by DDP, the rest follows by express courier at our cost. In 12 months we have had two late shipments and both were split-shipped at our expense.
06Plan your next order on our timeline
Sample parcels ship in 3 to 5 days at cost, refunded against bulk. MOQ on bulk is 11 pieces per model. Read our factory production flow, check how ring sizes and stock patterns actually move for your opening mix, and request a sample this week; it is the single fastest way to de-risk a first bulk order.
Finally, book the sample order the same week you agree on a spec, not after you have thought about it for a month. Samples take 3 to 5 days, and they are the cheapest insurance against a bulk order that misses the mark. The accounts that grow fastest with us are the ones who sample first and order second, every single time.
When you quote a lead time to your own customer, build in the same buffer we do. The reference points for the standards behind our stones and finishes are worth bookmarking: the GIA 4Cs page for the 4Cs your customers will ask about, and the Wikipedia entry on moissanite for the material spec. Knowing what your supplier is working against is the fastest way to stop promising dates you cannot keep.